Contaminated material removed and the site returned to rangeland.

Location
Mohall, North Dakota
Completed
July 2025
Aerial view of the excavation at MRPSU 36-23 South near Mohall.

Completed borings to assist environmental consultants with a site investigation, collecting samples for logging and laboratory analysis. Completed excavation and disposal of contaminated material, installed a geomembrane liner, backfilled clay and topsoil, ripped the site to reduce compaction, and completed seeding.

Project detail

Client and owner
Terracon and North Dakota Natural Resource Trust
Scope of work
Soil exploration, soil removal, soil replacement and reclamation
Key activities and methods
Drilling, Excavation, Dozer handling, Lining, Backfilling, and Seeding
Well sites
1
  • A dozer works the cut at MRPSU 36-23 South.
  • A tractor prepares the restored ground at MRPSU 36-23 South for seeding.

Have ground that needs to come back?

Tell us where the site is and what happened. We'll walk it with you and put a bid together.