Remediation, reclamation and site work for the State of North Dakota, the NDIC Oil & Gas Division, the North Dakota Natural Resource Trust, Terracon and the City of Tioga.

Tons of contaminated material removed
18,609
Well sites returned to farmland
20
Where Summit worksMap of northwest North Dakota, from the Montana line to east of Minot. Headquarters in Minot. Recent projects near Glenburn, Antler, Sherwood, Grano, Mohall, Berthold, Tioga and Alexander. An inset shows the region within the whole state; borehole services run statewide.CANADAMONTANAMinot HQGlenburn (2)Antler (2)Sherwood (2)GranoMohall (2)BertholdTioga (2)Alexander

Statewide, from Minot.

Most recent remediation work sits in the well fields north and west of Minot. The crew and the probe rig travel anywhere in the state.

Tons removed, by project

Tons of contaminated material removed, by project, largest first
ProjectTons removed
NDIC 2021 Bid Package #5Lando–Antler area, Fall 2021
43% of total
7,964
Aarhus 4-12R1-1Sherwood, July 2026
20% of total
3,745
Schwartz 1B2-3Antler, June 2026
15% of total
2,829
Amanda Kunkel 2R23-1Glenburn, May 2026
13% of total
2,425
Susan Anderson 1R17-4Grano, August 2026
5% of total
883
Nelson State 1B41-2Glenburn, June 2026
4% of total
763
Total18,609